Jakarta Plans to Finish the Pluit Flyover by April 2027

Jakarta Plans to Finish the Pluit Flyover by April 2027

Jakarta is resuming construction of the Pluit non-toll flyover in North Jakarta after work stopped in 2016.

The 1.5-kilometre road project began in 2015 and was halted after a policy change.

Jakarta Governor Pramono Anung has asked for work to continue, with completion targeted for April 2027.

Remaining work includes paving, drainage, lighting, traffic signs and finishing joints between sections of the bridge.

The project is intended to ease congestion in Pluit, Muara Karang and nearby areas.

After construction is complete, Jakarta's Bina Marga agency will maintain the flyover.

1 source

Related

What people are saying

Pramono AnungJakarta governor
Setelah hampir 11 tahun terhenti, pembangunan Jalan Layang Non-Tol (JLNT) Pluit akan kembali dilanjutkan
via CNBC Indonesia
Menindaklanjuti rapat terbatas di Kecamatan Penjaringan, kami mengunjungi lapangan dan berdiskusi dengan pihak pengembang agar JLNT ini bisa diresmikan April 2027. Semoga jalan layang ini dapat mengurangi kemacetan di kawasan Pluit, Muara Karang, dan sekitarnya
via CNBC Indonesia