Major bridge piling completed at closed Blue Mountains highway
Crews completed 54 major piles for a new bridge on the Great Western Highway at Victoria Pass in the Blue Mountains.
The highway has been closed since early March after engineers found serious cracking and ground movement in a stone causeway.
The closure has diverted up to 12,000 vehicles a day onto a route via Darling Causeway and Chifley Road, adding about 25 minutes to the journey.
The $200 million project is meant to restore traffic and improve the route, which has also affected businesses that rely on passing motorists.
The NSW government says the highway is on track to reopen to two lanes between April and June.
A third eastbound lane is also planned so drivers can pass slower vehicles along the 2.7-kilometre stretch uphill.
Crews are expected to begin work on that lane’s retaining wall over the next six weeks, but its final construction timeline will be set later.
Contractors have completed 54 major piles for a new bridge over Mitchell’s Causeway at Victoria Pass in the Blue Mountains.
The Great Western Highway has been closed at Victoria Pass since early March after engineers found serious cracking and ground movement.
The NSW government says the $200 million project is on track to reopen the highway to two lanes between next April and June.
The closure has forced up to 12,000 vehicles a day onto detours, placing pressure on motorists and businesses.
Plans for a third eastbound lane include 14 piles and 14 columns to support a new road deck.
- Who
- Contractors completed the piling. The NSW government is overseeing the project.
- What
- Major piling for a new bridge over Mitchell’s Causeway has been completed.
- When
- The work was reported on November 22, 2026. The highway has been closed since early March.
- Where
- Victoria Pass on the Great Western Highway in the Blue Mountains, New South Wales.
- Why
- Engineers found serious cracking and ground movement in the stone causeway, creating a risk it could collapse.
This story does not have two clearly opposing sides.
The Great Western Highway was closed at Victoria Pass after engineers found serious cracking and ground movement.
Contractors had completed driving 54 major piles into bedrock for the new bridge.
Construction crews are expected to begin work on the third lane’s retaining wall.
The NSW government says the highway is on track to reopen to two lanes of traffic.
- Major piles completed
- 54, each up to 20 metres long
- Project cost
- $200 million
- Traffic affected
- Up to 12,000 vehicles a day
- Detour
- Darling Causeway and Chifley Road; 25 minutes
- Planned third lane
- Two eastbound uphill lanes across Victoria Pass’s 2.7-kilometre length
What people are saying
With the potential for extra traffic on the roads as people visit family or head on holidays, motorists should plan ahead, take it easy and show some patience to ensure everyone gets there and back safely