Science & Tech · Big Tech & Internet · 3 hrs ago

Spain eases some proposed rules for data centres

Spain eases some proposed rules for data centres

Spain’s government has revised proposed rules for data centres and sent the new draft to the Council of State for review.

The rules would apply to facilities with electrical capacity of at least 10 megawatts, up from the original one-megawatt threshold.

Data centres would still have to show that 80% of their electricity comes from renewable sources, measured hour by hour.

They may take up to five years to meet that target, with lower renewable-use requirements during the transition.

To use the transition, centres must join a system that can automatically reduce their power and disconnect them when the grid operator requests it.

The industry says the hourly target could raise costs and put investment at risk, while the government says the rules aim to limit pressure on water resources and electricity prices.

The Council of State will review the draft before the government considers it for final approval.

4 sources

Related

What people are saying

Government sourcesSpanish government representatives
If the new demand that arrives puts pressure on the system, the first to be disconnected will not be the traditional industry we already had nor household consumers, but the data centre.
via El País