Business · Companies · 9 hrs ago
EDF nears €14 billion civil works contract for six EPR2 reactors
EDF is finalising a civil works contract for France’s planned EPR2 nuclear reactors with a consortium including Vinci, Bouygues and Eiffage.
The deal also includes construction companies NGE and Fayat, and is valued at about €14 billion in current euros.
The work is part of a programme for six new reactors, whose total cost is estimated at €72.8 billion.
EDF says standardising construction and repeating methods between reactor pairs could help shorten building times and improve efficiency.
The contract still needs approval from EDF’s board, which is expected by the end of the month.
A final investment decision is expected by year-end, and the first two reactors are planned for Penly, with service expected in 2038.
EDF is finalising a civil works contract for France’s six planned EPR2 nuclear reactors, reportedly worth about €14 billion.
The contract is being negotiated with a consortium involving Vinci, Bouygues, Eiffage, NGE and Fayat.
EDF’s board is expected to approve the agreement by the end of November, before it is officially announced.
The deal is a step towards a final investment decision on the project, expected by the end of 2026.
The six reactors are estimated to cost €72.8 billion in total, with the first two planned to enter service at Penly in 2038.
- Who
- EDF and a consortium involving Vinci, Bouygues, Eiffage, NGE and Fayat.
- What
- They are finalising a civil works contract for six EPR2 reactors, reportedly worth about €14 billion.
- When
- The contract is expected to be approved by EDF’s board by the end of November 2026. A final investment decision is expected by the end of 2026.
- Where
- The reactors are planned for Penly, Gravelines and Bugey in France.
- Why
- The agreement would help secure a large part of the project’s estimated cost and support standardised construction methods.
This story does not have two clearly opposing sides.
Emmanuel Macron announced a programme to build six new nuclear reactors, with an option for eight more.
EDF’s board is expected to validate the civil works agreement.
The final investment decision on the overall project is expected.
The first two reactors are planned to enter service at Penly.
- Reported contract value
- About €14 billion today, or €12 billion in 2020 euros
- Consortium
- Vinci, Bouygues, Eiffage, NGE and Fayat
- Total estimated cost
- €72.8 billion for six EPR2 reactors
- Planned locations
- Penly, Seine-Maritime; Gravelines, Nord; and Bugey, Ain
- First planned start of service
- 2038, for the first two reactors at Penly
What people are saying
a proposal likely to meet our expressed needs has been submitted by a group bringing together several major players in the sector for the civil works of the EPR2 programme
to guarantee maximum replicability from one pair of reactors to another, relying in particular on the standardisation and reproduction of civil engineering methods