Business · Energy & Commodities · 2 hrs ago
Trans Mountain shipments rise after pipeline capacity upgrade
Trans Mountain oil shipments from British Columbia rose sharply in October after the company finished a pipeline upgrade.
The line carries crude from Alberta to the coast and can now move 980,000 barrels a day.
The upgrade used drag-reducing agents to cut friction inside the pipeline, adding about 90,000 barrels a day of capacity.
Asian buyers are driving demand for Canadian oil, with China receiving most of the tankers that left the Westridge terminal in October.
Thirty tankers departed that month, a record, carrying 15.9 million barrels of oil.
Trans Mountain has applied for approval for a larger project that could add another 210,000 barrels a day.
A decision on technical approval is expected by April; the company would also need oil companies to commit to using the expanded line before making a final investment decision.
Trans Mountain crude shipments from British Columbia rose sharply in October after the company completed a pipeline capacity project.
The system can now carry 980,000 barrels of oil a day from Alberta to the coast.
Thirty tankers left the Westridge Marine Terminal in October, six more than in September, and exports reached 15.9 million barrels.
Asia-Pacific was the main destination, with China receiving the largest share.
Trans Mountain has applied for approval for another project that would increase capacity by a further 210,000 barrels a day.
- Who
- Trans Mountain, the pipeline operator, and oil shippers using its system.
- What
- Crude oil shipments rose after a capacity upgrade. Trans Mountain has also applied to expand capacity further.
- When
- Shipments rose in October; the upgrade was completed that month.
- Where
- Oil travels from Alberta to the British Columbia coast, with tankers departing from Westridge Marine Terminal in Burnaby.
- Why
- Alberta production growth and demand for Canadian crude, particularly in Asia, are driving demand for pipeline capacity.
This story does not have two clearly opposing sides.
Trans Mountain’s expanded system started operating.
The pipeline operated at 90 per cent of capacity, according to federal Crown corporation data.
Trans Mountain completed a project that increased capacity by roughly 90,000 barrels a day.
Thirty tankers departed Westridge, and export volumes reached 15.9 million barrels.
Trans Mountain anticipates a regulatory decision on the technical aspects of its proposed larger optimization project.
- Current capacity
- 980,000 barrels a day
- Capacity added by October upgrade
- Roughly 90,000 barrels a day
- October tanker departures
- 30
- October export volumes
- 15.9 million barrels
- Proposed further capacity increase
- 210,000 barrels a day
- Westridge departures since May 2024
- 722 tankers
What people are saying
We are seeing record production out of the basin, and we’re also seeing record demand coming in on the Pacific Coast
reimagining what their supply strategy should be
ways that we were able to complete that 2½ months ahead of schedule and put it into service
We’re anticipating that we would have a regulatory decision on the technical aspects by April, and we need to have the commercial underpinnings for that to move forward with a final investment decision