Uganda Delays First Oil Production Until Mid-2027
Uganda has pushed its first oil production and exports back to before the end of June 2027 because equipment deliveries were delayed.
Officials say supply-chain problems linked to the war in Iran held up parts needed for production and transport systems.
Commercial oil reserves were discovered in Uganda in 2006, but production has yet to begin.
The country’s Tilenga and Kingfisher projects and the export pipeline still need final work and testing before oil can flow.
Uganda expects to begin with about 25,000 barrels a day from Kingfisher, with output later increasing as the projects ramp up.
The delay puts projected oil revenue of 1.44 trillion Ugandan shillings at risk in the 2026/2027 budget.
Once production starts, officials say oil could bring the government between $1.5 billion and $2.5 billion a year.
The next step is completing and testing the facilities and pipeline before exports can begin.
Uganda has delayed the start of its first commercial oil production and exports until before the end of June 2027.
Officials attributed the delay to supply chain bottlenecks and disruptions linked to the war in Iran, which held up equipment and materials.
The delay affects projects and infrastructure that must be completed and tested before production and exports can begin.
Uganda’s FY 2026/2027 budget projected petroleum revenues of Ush 1.44 trillion, about $380 million.
- Who
- Uganda’s National Oil Company and Petroleum Authority announced the delay.
- What
- Uganda’s first commercial oil production and crude exports have been pushed back until before the end of June 2027.
- When
- Announced in November 2026; production is now expected before the end of June 2027.
- Where
- Uganda, with crude exports planned through a pipeline to Tanga Port in Tanzania.
- Why
- Supply chain bottlenecks and disruptions linked to the war in Iran delayed deliveries of key equipment and materials.
This story does not have two clearly opposing sides.
Commercial oil reserves were first discovered in Uganda.
Uganda’s finance minister told parliament that the FY 2026/2027 budget projected petroleum revenues of Ush 1.44 trillion.
The Bank of Uganda raised its benchmark policy rate by 225 basis points to 12.0%.
Lawmakers put the Tilenga Project at 78% complete and the Kingfisher development at 90%.
Officials announced that first oil production and exports had been delayed until before the end of June 2027.
- Revised target
- Before the end of June 2027
- Budgeted petroleum revenues
- Ush 1.44 trillion, about $380 million
- EACOP length
- 1,443 kilometres
- EACOP construction
- More than 90% complete
- Projected combined peak output
- About 230,000 barrels per day
- Initial Kingfisher production
- Around 25,000 barrels per day