Business · Companies · 1 hr ago
Telus withdraws from two planned Vancouver AI data centres
Telus has withdrawn from two planned AI data centres in Vancouver, saying it will not proceed with the projects.
The company had planned them with Vancouver developer Westbank to meet growing demand for computing power from Canadian businesses and government.
The projects faced strong local opposition, including protests over environmental, community and housing impacts.
The facilities were expected to use up to 63,000 Nvidia chips and draw as much as 163 megawatts of electricity; one was planned to open in 2026 and the other in 2029.
Westbank says it will continue developing the centres with a new partner, which has not yet been announced.
Telus will expand its Kamloops facility instead and is also assessing other partnerships and locations for its computing services.
The decision matters as the federal government seeks more domestic computing capacity and less reliance on U.S. cloud providers.
Telus is ending its participation in two planned artificial intelligence data centres in Vancouver.
The company announced its decision on Sunday after local opposition and shifts in its AI investment strategy.
Westbank said it would continue developing the projects with a new, unannounced partner.
Telus had planned to supply the centres with about 63,000 Nvidia chips and up to 163 megawatts of electricity.
Telus said it would continue expanding its facility in Kamloops, British Columbia, and assess new partnerships and locations.
- Who
- Telus Corp. is withdrawing from the projects. Westbank Corp. plans to continue developing them with a new partner.
- What
- Telus is ending its participation in two planned AI data centres.
- When
- Sunday; the article was published on November 16, 2026.
- Where
- Vancouver, British Columbia: one planned site was downtown and the other was in Mount Pleasant.
- Why
- Telus did not provide an explanation. The article cites shifts in its AI investment strategy and a source’s claim that a lack of local support contributed to the decision.
Vancouver project opponents
Telus and Westbank
Project impacts
Vancouver project opponents
Opponents called for the projects to be cancelled over environmental, community and housing concerns.
Telus and Westbank
Telus had cited growing demand for computing power among Canadian businesses and government; Westbank said it would continue developing the centres.
Telus said it would co-develop two Vancouver data centres with Westbank.
Hundreds of people protested in Vancouver and called for the projects to be cancelled.
Telus said it had decided not to proceed with the projects.
- Planned chips
- About 63,000 Nvidia chips
- Planned electricity use
- Up to 163 megawatts
- Downtown centre
- Planned to come online in 2029
- Mount Pleasant facility
- Expected to open at the end of 2026
- Kamloops facility
- Telus said it would continue expanding it
What people are saying
has decided not to proceed
These new sites will scale our capacity to meet the growing demand we are seeing at our existing facilities, which leverage clean, renewable energy and industry-leading power efficiency