Business · Economy · 17 hrs ago
Economic pressures, not bureaucracy alone, slow French homebuilding
France is building fewer homes, and projects can take longer to complete than they did before.
A housing project can now take five years, up from three, according to Nexity chief executive Véronique Bédague.
In apartment construction, starts fell by a quarter between 2019 and 2025.
Appeals against building permits can delay projects, although France’s Court of Accounts says local authorities generally issue permits on time.
The bigger obstacle is finding buyers in a difficult economy: construction costs have risen 19% since 2019, and average interest rates are now 4%.
Banks also commonly require developers to have sold 50% to 60% of homes before financing a project, making it harder to get construction started.
The account gives no specific next steps for changing the situation.
French homebuilding has slowed, with economic pressures identified as a bigger obstacle than bureaucracy alone.
Housing starts in multi-unit buildings fell by a quarter between 2019 and 2025.
Construction costs rose 19% since 2019, while average interest rates reached 4%.
Banks now commonly require 50% to 60% of homes to be pre-sold before financing projects.
A 19-home project in Hauts-de-Seine began in 2019, but its keys were handed over only in 2026.
- Who
- French housing developers and homebuyers are affected. Nexity CEO Véronique Bédague cited bureaucracy, while property-sector experts pointed to economic conditions.
- What
- Homebuilding is slowing, as developers face delays and difficulty finding buyers and financing.
- When
- The report was published on November 21, 2026. It describes construction trends from 2019 to 2025 and a project completed in 2026.
- Where
- France, including a 19-home project in Hauts-de-Seine.
- Why
- Building costs and interest rates have risen, and banks require more homes to be pre-sold. Administrative procedures and appeals also cause delays.
Véronique Bédague and developers citing bureaucracy
Property-sector experts emphasizing economic pressures
Main cause of delays
Véronique Bédague and developers citing bureaucracy
More procedures and complex mechanisms slow projects.
Property-sector experts emphasizing economic pressures
The harder problem is finding buyers and securing financing in difficult economic conditions.
The Hauts-de-Seine project for 19 homes dates back to this year.
Véronique Bédague said procedures were adding to the time needed to make decisions and build.
Housing starts in multi-unit buildings had fallen by a quarter compared with 2019.
The keys to the 19 homes in the Hauts-de-Seine project were handed over.
- Housing starts
- Multi-unit starts fell by a quarter between 2019 and 2025
- Construction costs
- Up 19% since 2019
- Average interest rate
- 4%
- Banks’ pre-sale requirement
- Commonly 50% to 60% of homes
- Hauts-de-Seine project
- 19 homes; project began in 2019 and keys were handed over in 2026
What people are saying
The decision-making time is slower, the mechanisms are more complex. I think we are adding procedure upon procedure.
The time it takes to submit a new permit, obtain it, have it cleared... And unfortunately, the developer who carried out this project faced 12 appeals against the building permit.
Time is money. During that time, financing costs keep running.
Because the risk that the homes will not sell, in the current economic circumstances, must be controlled.