Economic pressures, not bureaucracy alone, slow French homebuilding

Economic pressures, not bureaucracy alone, slow French homebuilding

France is building fewer homes, and projects can take longer to complete than they did before.

A housing project can now take five years, up from three, according to Nexity chief executive Véronique Bédague.

In apartment construction, starts fell by a quarter between 2019 and 2025.

Appeals against building permits can delay projects, although France’s Court of Accounts says local authorities generally issue permits on time.

The bigger obstacle is finding buyers in a difficult economy: construction costs have risen 19% since 2019, and average interest rates are now 4%.

Banks also commonly require developers to have sold 50% to 60% of homes before financing a project, making it harder to get construction started.

The account gives no specific next steps for changing the situation.

1 source

Related

What people are saying

Véronique BédagueNexity CEO
The decision-making time is slower, the mechanisms are more complex. I think we are adding procedure upon procedure.
via franceinfo
Marc GédouxPresident of the FFB Grand Paris Housing division
The time it takes to submit a new permit, obtain it, have it cleared... And unfortunately, the developer who carried out this project faced 12 appeals against the building permit.
via franceinfo
Time is money. During that time, financing costs keep running.
via franceinfo
Henry Buzy-CazauxPresident of the Institute of Management of Real Estate Services
Because the risk that the homes will not sell, in the current economic circumstances, must be controlled.
via franceinfo