Energy officials warned Victoria’s government that attracting data centres could put major pressure on the state’s electricity system.
The March 2026 briefing said plans to attract up to $25 billion in data centre investment could cause a sudden rise in electricity demand.
That comes as ageing coal-fired generators are due to retire, while Victoria aims to phase out coal-fired power by 2035.
The government had limited oversight of proposed projects, so former energy minister Lily D’Ambrosio approved plans requiring five electricity distributors to notify her before offering grid connections to projects exceeding 30 megawatts.
The extra demand could threaten the clean energy transition if it is not matched by enough power and grid capacity.
NextDC delayed an expansion of its West Footscray site after residents opposed power-line works, and the major parties have faced pressure to rethink their support for the industry ahead of the state election.
Senior Victorian energy officials warned that plans to attract data centres could pose a major challenge to the state’s electricity system.
A March 2026 briefing said the projects could cause a sudden surge in electricity demand as ageing coal-fired generators retire.
The government approved a plan requiring five power distributors to notify the energy minister before offering grid connections to projects exceeding 30 megawatts.
The warning came as the Labor government pursued up to $25 billion in data centre investment.
Community opposition delayed electricity network works needed for an expansion of NextDC’s West Footscray data centre.
- Who
- Victorian energy officials warned the Labor government. The briefing was prepared for then energy minister Lily D’Ambrosio.
- What
- Officials warned that data centre growth could strain Victoria’s electricity system and complicate its clean energy transition.
- When
- The briefing was dated March 2026. The documents were reported in November 2026.
- Where
- Victoria, Australia.
- Why
- Officials said projected electricity demand could surge, while the government lacked enough oversight of major projects’ effects on the grid.
Labor government
Victorian energy officials
Investment
Labor government
The government pursued data centre investment as an economic opportunity for Victoria.
Victorian energy officials
Officials warned that projected demand posed a major structural challenge to the electricity system.
Grid oversight
Labor government
The government approved a plan for power distributors to notify the energy minister about grid connection offers to projects exceeding 30 megawatts.
Victorian energy officials
Officials said the government needed greater visibility of how large projects would affect the grid individually and collectively.
The Australian Industry Group urged ministers to prepare for a range of data centre growth scenarios.
A department briefing warned that projected data centre electricity demand posed a major structural challenge.
Jemena paused works to replace power poles after residents blockaded the distributor.
NextDC delayed the West Footscray expansion and cut its earnings forecast, according to the article.
- Potential investment
- Up to $25 billion
- Grid notification threshold
- More than 30 megawatts
- Distributors named
- AusNet, CitiPower, Jemena, Powercor and United Energy
- West Footscray project
- NextDC data centre expansion
- Coal phase-out target
- 2035
3 sources
What people are saying
While this presents an economic opportunity for Victoria, the scale of projected energy demand from Victoria’s data centre industry presents a major structural challenge for the state’s electricity system.
It could upend the energy transition in a huge way