Officials warned Victoria’s data centre push could strain the power grid

Officials warned Victoria’s data centre push could strain the power grid

Energy officials warned Victoria’s government that attracting data centres could put major pressure on the state’s electricity system.

The March 2026 briefing said plans to attract up to $25 billion in data centre investment could cause a sudden rise in electricity demand.

That comes as ageing coal-fired generators are due to retire, while Victoria aims to phase out coal-fired power by 2035.

The government had limited oversight of proposed projects, so former energy minister Lily D’Ambrosio approved plans requiring five electricity distributors to notify her before offering grid connections to projects exceeding 30 megawatts.

The extra demand could threaten the clean energy transition if it is not matched by enough power and grid capacity.

NextDC delayed an expansion of its West Footscray site after residents opposed power-line works, and the major parties have faced pressure to rethink their support for the industry ahead of the state election.

3 sources

Related

What people are saying

DEECA briefing to Lily D’AmbrosioDepartment briefing
While this presents an economic opportunity for Victoria, the scale of projected energy demand from Victoria’s data centre industry presents a major structural challenge for the state’s electricity system.
via The Age
Bruce MountainVictoria University Energy Policy Centre director
It could upend the energy transition in a huge way
via The Age
There would simply be no way to close the coal generators and meet that demand.
via The Age