Politics · United Kingdom · 1 week ago
Asbestos finds add pressure to restore the UK Parliament
The Palace of Westminster in London has more than 1,650 known asbestos items, including insulation, roofing and floor tiles.
That is 500 more than in 2021, after surveys found additional items ahead of a planned refurbishment.
Most are classed as low risk because they are concealed, but almost 200 are considered medium risk and may need remedial work.
The Commons public accounts committee says delay raises the risk of a major failure, including fire, and could endanger lives and disrupt Parliament.
The work could cost up to £40bn and take as long as 61 years, while each year of delay adds an estimated £420m to the programme’s lifetime cost.
Parliament is considering options for the restoration, and votes on the project are expected later this year.
A first phase of work is also under consideration, but the final choice of restoration plan is not expected until 2030.
MPs may vote in December on starting preparatory work for restoring the Palace of Westminster, though the proposal would not decide the final restoration plan.
The work would include procurement and building surveys and is estimated to cost £3 billion over seven years.
A Commons committee has warned that delays increase costs and raise the risk of a major failure that could endanger lives.
The restoration could cost up to £40 billion and take as long as 61 years, according to estimates cited by the reports.
The plans face political disagreement, with Conservative Party leaders reportedly intending to tell their MPs to oppose the preparatory work.
- Who
- UK MPs are expected to consider a vote on preparatory restoration work. Conservative Party leaders reportedly intend to oppose it.
- What
- The proposed vote would begin preparatory work, including procurement and building surveys. It would not select the final restoration plan.
- When
- A vote is being discussed for early December 2026.
- Where
- The Palace of Westminster and the wider parliamentary estate in London.
- Why
- The building has ageing infrastructure and safety risks, while delays are increasing the projected cost of restoration.
Supporters of preparatory work
Opponents of preparatory work
Starting work
Supporters of preparatory work
The Commons public accounts committee and Geoffrey Clifton-Brown urge the government to proceed, citing rising costs and safety risks.
Opponents of preparatory work
Conservative Party bosses reportedly plan to instruct their MPs to block the preparatory works; Kemi Badenoch has called the restoration plans “out of control.
Cost and risk
Supporters of preparatory work
Supporters say each year of delay adds an estimated £420 million and could increase the risk of a catastrophic event.
Opponents of preparatory work
Badenoch has criticised the project as a “basket case white elephant project”; the sources do not give a detailed explanation from Conservative Party bosses for opposing this vote.
Parliamentarians voted to move out of the central London site to allow extensive repairs.
Alan Campbell told MPs that postponing restoration increases the cost of maintaining and eventually repairing the building.
The Commons public accounts committee warned of rising costs and the risk of a catastrophic failure.
Government whips are reported to be discussing a debate and vote on starting preparatory works.
The final option for wholesale restoration is expected to be decided.
- Preparatory works
- Estimated at £3 billion over seven years
- Annual delay
- Estimated to add £420 million to lifetime restoration costs
- Full decant option
- Up to £15.6 billion and 24 years
- Enhanced maintenance and improvement plus
- About £39 billion and up to 61 years
- Current maintenance bill
- About £1.5 million a week, expected to rise to £2 million
- Known asbestos items
- More than 1,650 across the Palace of Westminster and wider parliamentary estate
7 sources
Parliament restoration delays 'frustrating', says Commons Speaker
Notre-Dame was restored in five years and under budget. But the Palace of Westminster? No chance | Simon Jenkins
Centuries-old UK parliament risks ‘catastrophic failure’ over delayed revamp
More asbestos found in Parliament, as MPs urged to get on with revamp
UK Parliament risks ‘catastrophic failure’ over delayed renovation
Burnham revives hopes UK's crumbling parliament will get a fix
Houses of Parliament at risk of ‘Notre Dame-style fire’ as renovation costs rise
What people are saying
These are not notional possibilities, but real and rising risks.
The longer we postpone it, the more it costs not just to keep this place functioning, but to eventually get round to doing something about it.
out of control
absolute priority is the safety of the those who work on and visit the parliamentary estate