Business · Companies · 1 day ago
Tests begin on high-speed rail link to Bursa
Technical testing has started on the Osmaneli–Bursa rail section in Turkey, part of the Bandırma–Bursa–Yenişehir–Osmaneli high-speed rail project.
Transport and Infrastructure Minister Abdulkadir Uraloğlu said construction work on the section’s infrastructure and track systems is complete.
The line is being tested before it can enter service, including checks on its signalling, overhead power equipment and connection to the Ankara–Istanbul high-speed route.
More tests are planned, including checks of train control and railway communications systems.
The project will connect Bursa to Turkey’s high-speed rail network through Osmaneli.
Journeys from Bursa to Ankara and Istanbul are expected to take 2 hours 15 minutes once the section is complete.
The line will open after testing and certification are finished.
Testing has begun on the Osmaneli–Bursa section of the Bandırma–Bursa–Yenişehir–Osmaneli high-speed rail project.
Transport and Infrastructure Minister Abdulkadir Uraloğlu said infrastructure and track construction on the section is complete.
Testing includes signalling, overhead wires and dynamic acceleration, with further system and integration tests planned.
The section is intended to connect Bursa to the Ankara–Istanbul high-speed rail line through Osmaneli.
The minister said travel between Bursa and Ankara or Istanbul would take 2 hours and 15 minutes once the link is complete.
- Who
- Transport and Infrastructure Minister Abdulkadir Uraloğlu announced that testing had begun.
- What
- Tests have started on the Osmaneli–Bursa section of the Bandırma–Bursa–Yenişehir–Osmaneli high-speed rail project.
- When
- The announcement was published on 21 November 2026. Testing began before the announcement; an exact start date is not stated.
- Where
- On the Osmaneli–Bursa section in Turkey, which is planned to connect Bursa with the Ankara–Istanbul high-speed rail line.
- Why
- To check the rail line’s systems and prepare it for safe operation, and to connect Bursa to the high-speed rail network.
This story does not have two clearly opposing sides.
Road geometry and static catenary measurements were completed.
Signalling power system tests began.
Catenary hot running tests were being carried out, with dynamic acceleration tests and dynamic catenary measurements planned during the month.
Sabah reported that testing had begun on the Osmaneli–Bursa section.
- Project
- Bandırma–Bursa–Yenişehir–Osmaneli High-Speed Train Project
- Section under testing
- Osmaneli–Bursa
- Travel time
- 2 hours 15 minutes between Bursa and Ankara or Istanbul
- Minister
- Abdulkadir Uraloğlu
- Announcement date
- 21 November 2026
What people are saying
Testlerin ve sertifikasyon sürecinin tamamlanmasının ardından Bursa’yı hızlı tren ağıyla buluşturacağız.
Osmaneli–Bursa kesiminde altyapı ve üstyapı çalışmalarını tamamladık, hattımızda test sürecini başlattık.