Mysuru grade separator at Kempegowda Circle due by June 2027

Mysuru grade separator at Kempegowda Circle due by June 2027

Mysuru’s grade separator at Kempegowda Circle is due by June 2027, MP Yaduveer Krishnadatta Chamaraja Wadiyar said after inspecting the work.

The grade separator is part of a ₹700 crore highway improvement project, and its construction costs ₹120 crore.

The National Highways Authority of India is carrying out the work, and girders are scheduled to be installed next month.

The flyover section is expected to open by March 2027, before the rest of the project is finished.

The junction connects the Mysuru-Bengaluru highway with the Ring Road and has become a traffic bottleneck.

Of 350 trees affected, 278 were transplanted, and Yaduveer said nearly 95% had survived.

Officials were told to meet the deadline, maintain quality and limit disruption, while the health of the transplanted trees continues to be monitored.