Business · Energy & Commodities · 11 hrs ago

Three steam generators installed at Zhangzhou nuclear plant’s fourth unit

Three steam generators installed at Zhangzhou nuclear plant’s fourth unit

Three steam generators were installed at Unit 4 of the Zhangzhou nuclear power plant on November 20.

The plant is in Yunxiao County, in Fujian province in southeastern China.

The unit is part of the Hualong One project, China’s domestically designed third-generation nuclear technology.

Each generator is about 21 metres long and weighs around 370 tonnes, making installation a precision task.

The generators help produce steam and contain radioactivity, and also help remove heat from the reactor core during operation.

Zhangzhou’s site is planned to have six Hualong One units; its first two units are already in commercial operation.

The installation marks a construction milestone, but no timetable for Unit 4 to begin operating was given.