Jakarta MRT completes rail installation from Bundaran HI to Monas
Jakarta MRT has completed rail installation between Bundaran HI and Monas on the north-south line extension in Indonesia's capital.
The work included rails in the tunnels and a stabling track near Thamrin station.
The Phase 2A project was 66.13% complete as of October 25, 2026.
The Bundaran HI–Monas section is targeted to open by the end of 2027, while the extension onward to Kota is due by the end of 2029.
Construction teams will continue rail work toward Kota, after carrying out technical tests on completed sections.
The rails were made in Fukuoka, Japan, and use concrete sleepers designed for durability and low maintenance.
Jakarta MRT has completed rail installation on the Bundaran HI–Monas section of Phase 2A.
The installation and track concreting took about 10 months, from December 2025 to October 2026.
Construction progress on Phase 2A stood at 66.13% as of 25 October 2026.
MRT Jakarta targets the Bundaran HI–Monas section to begin operating by the end of 2027.
Work on the rail is to continue from section 1 toward section 2, reaching Kota.
- Who
- PT MRT Jakarta (Perseroda) completed the rail installation.
- What
- Rail installation on the Bundaran HI–Monas section is complete.
- When
- The work ran from December 2025 to October 2026.
- Where
- The section runs from Bundaran HI to Monas in Jakarta.
- Why
- The sources say technical tests checked that the work met specifications and safety standards.
This story does not have two clearly opposing sides.
Rail installation and concreting work began.
Rail installation and concreting work on the Bundaran HI–Monas section was completed.
Phase 2A construction progress was reported at 66.13%.
MRT Jakarta targets the Bundaran HI–Monas section to begin operating.
- Phase 2A progress
- 66.13% as of 25 October 2026
- Rail work period
- December 2025 to October 2026
- Section 1 target
- Operation by the end of 2027
- Northern tunnel main track
- 2.247 kilometres
- Southern tunnel main track
- 2.236 kilometres
- Stabling line
- 246 metres