Science & Tech · Science & Environment · 4 hrs ago
IEA expects data centre electricity use to double by 2030
The International Energy Agency expects data centre electricity use to double by 2030, from about 500 terawatt-hours today to 1,000 terawatt-hours.
It says AI servers will drive about three-quarters of the increase by 2030.
The IEA also expects global electricity demand to rise 36.6 per cent between 2025 and 2035, reaching 39,042 terawatt-hours.
More air conditioning, as incomes rise and temperatures climb, is a major reason for the higher forecast.
Cooling demand in buildings now exceeds heating demand, the IEA says, and cooling could account for 30 per cent of peak electricity demand by 2035.
Data centres use a small share of global electricity, but their demand is concentrated, with China, the European Union and the United States accounting for more than 80 per cent of projected use in 2035.
The extra demand could strain power systems, while coal and gas currently supply about 60 per cent of the electricity used by data centres.
The IEA projects that data centre electricity use will double to about 1,000 terawatt-hours by 2030.
AI servers are expected to account for about three-quarters of the growth in data centre demand to 2030.
The agency says emissions linked to data centres are on track to rise by 70 per cent by 2030.
Data centres are expected to use about 1,500 terawatt-hours of electricity by 2035.
The IEA says data centre demand is adding strain to some electricity markets and supply chains.
- Who
- The International Energy Agency (IEA) made the projection.
- What
- Data centre electricity use is projected to double by 2030, reaching about 1,000 terawatt-hours.
- When
- By 2030.
- Where
- Worldwide.
- Why
- The IEA attributes the increase mainly to the expansion of artificial intelligence and the growth in data centres.
This story does not have two clearly opposing sides.
Annual global shipments of AI servers climbed eighteen-fold, according to the IEA analysis.
Global data centre capacity climbed tenfold to 17 gigawatts, according to the IEA.
Data centre electricity demand is projected to double from about 500 to 1,000 terawatt-hours.
Data centre electricity use is projected to reach 1,500 terawatt-hours.
- Data centre electricity use today
- About 500 terawatt-hours
- Projected data centre electricity use by 2030
- 1,000 terawatt-hours
- AI share of data centre growth to 2030
- About three-quarters
- Projected data centre electricity use by 2035
- 1,500 terawatt-hours
- Projected rise in data centre emissions by 2030
- 70 per cent
3 sources
AI data center power demand will double by 2030 thanks to $4 trillion in spending, adding an entire Great Britain to energy strain
Global electricity demand to rise about 37 per cent by 2035, with heatwaves and AI pushing projections higher: IEA
Datacentres to create 70% more carbon emissions by 2030, IEA report warns
What people are saying
I don’t see any credible pathway for the energy world to return to the way it was before
Already today, for the first time in energy history, demand for cooling in buildings is overtaking that for heating.
AI could help to optimise the electricity system and bring down costs, but for the moment, surging demand from data centres is amplifying strains in some markets and supply chains