Business · Energy & Commodities · 5 hrs ago

AI data centers turn to converted jet engines as grid power lags

AI data centers turn to converted jet engines as grid power lags

AI data centers are turning to converted jet engines to generate their own electricity as grid connections and new power equipment face long delays.

The engines come from retired aircraft, are rebuilt to run on natural gas and can be operating much sooner than some grid connections.

In Northern Virginia, connecting 100 megawatts to the grid takes about seven years, while a data center using jet-engine units could be running in 24 months, according to an energy analyst cited in the story.

Elon Musk’s xAI has installed eight units in Mississippi to help power its Colossus 2 data center in Memphis.

OpenAI and data center builder Crusoe have also used or ordered converted turbines for a campus in Abilene, Texas.

The engines are less efficient and pollute more than turbines made for conventional gas plants, so they may be a short-term option.

Power delays have already affected business plans: Microsoft withdrew as the anchor customer for a data center in Loughton, England, after the utility said it could not supply enough electricity until the early to mid-2030s.

The story gives no specific next step, but says most new power capacity is expected to come online by 2031.

1 source

Related

What people are saying

Audun MartinsenRystad Energy analyst
It’s all about getting power as fast as possible
via The New York Times
they can have a data center running in 24 months
via The New York Times