Consortium wins contract to build Cuernavaca convention centre
A consortium led by Grupo Alavez Lambarri won the contract to build a convention centre in Cuernavaca, in the Mexican state of Morelos.
Its bid was 660.9 million pesos, below the government’s 700 million peso estimate.
The project drew 18 bids, but six firms reached the final evaluation; the winning consortium scored 95.4 points out of 100.
The centre is planned to hold 3,500 people and could also serve as a cultural venue.
The state government is expected to run it with its tourism department once construction is complete.
The project aims to boost business tourism and support local activity in hotels, restaurants, transport and other services.
Construction is expected to begin after the contract is signed, with a 488-day completion period.
A consortium led by Grupo Alavez Lambarri won the contract to build the Cuernavaca Convention Centre in Morelos.
The bid scored 95.4 points out of 100 and offered to do the work for 660.9 million pesos.
The contract award was recorded on October 29, and the contract was scheduled to be signed on November 3.
Construction was expected to start the following day and take 488 calendar days.
The planned venue is expected to hold 3,500 people and support business tourism and other economic activity.
- Who
- A consortium led by Grupo Alavez Lambarri, together with Consorcio Constructor AA and Consorcio Constructor Doble AA.
- What
- It won the contract to build the Cuernavaca Convention Centre.
- When
- The award was recorded on October 29, 2026. The contract was scheduled to be signed on November 3, with work expected to start the next day.
- Where
- Cuernavaca, in the state of Morelos, Mexico.
- Why
- The centre is intended to support business tourism and economic activity in the state.
This story does not have two clearly opposing sides.
The award decision was recorded, naming the Grupo Alavez Lambarri-led consortium as the winner.
The contract was scheduled to be signed at the SICT centre in Cuernavaca.
Construction was expected to begin.
The stated period for building the convention centre.
- Winning consortium
- Grupo Alavez Lambarri, Consorcio Constructor AA and Consorcio Constructor Doble AA
- Bid score
- 95.4 out of 100
- Bid price
- 660.9 million pesos
- Estimated project value
- 700 million pesos
- Construction period
- 488 calendar days
- Planned capacity
- 3,500 people
What people are saying
The proposal submitted by Grupo Alavez Lambarri in joint participation with Consorcio Constructor AA and Consorcio Constructor Doble AA is determined to be the winner of this tender