Business · Energy & Commodities · 4 hrs ago
Rome waste-to-energy plant secures €1.058 billion in financing
RenewRome and its shareholders secured €1.058 billion in long-term green financing for a new waste-to-energy plant in Rome.
The facility is planned for Santa Palomba, in the Rome area, and will be built and operated under a concession with Rome lasting about 33 years.
It is designed to handle about 600,000 tonnes of urban waste a year, using waste that cannot be recycled further to produce energy.
The plant is expected to generate 530 gigawatt-hours of electricity each year, described as enough for about 200,000 households.
The financing runs for 19.5 years and is backed by a Sace guarantee, with 17 financial institutions involved in the operation.
The financing is now finalized, but the information provided does not give a construction start date or an opening date.
RenewRome and its shareholders finalized €1.058 billion in long-term green project financing for Rome’s new waste-to-energy plant.
The plant is planned for the Santa Palomba area and will be built and operated under a concession with Rome lasting about 33 years.
The financing runs for 19.5 years and is backed by a Sace Archimede guarantee on the project’s long-term debt.
The plant is designed to process about 600,000 tonnes of municipal waste a year and generate 530 GWh of net electricity.
RenewRome said the project will recover energy from waste that cannot be recycled further.
- Who
- RenewRome and its shareholders: Acea Ambiente, Suez Italy, Kanadevia Inova, Vianini Lavori and Rmb.
- What
- They finalized €1.058 billion in long-term green project financing for a waste-to-energy plant.
- When
- 19 November 2026.
- Where
- The plant is planned for the Santa Palomba area of Rome.
- Why
- To finance construction and operation of the plant, which will process residual municipal waste and recover energy.
This story does not have two clearly opposing sides.
This story does not have a timeline yet.
- Financing
- €1.058 billion
- Financing term
- 19.5 years
- Concession with Rome
- About 33 years
- Planned location
- Santa Palomba, Rome
- Annual waste capacity
- About 600,000 tonnes
- Net electricity production
- 530 GWh
What people are saying
The success of the financing, made possible by the confidence of Sace and 17 leading national and international financial institutions, confirms the solidity of the project and its strategic value for the area.
We are proud to contribute, together with our shareholders and Roma Capitale, to the creation of a modern and sustainable infrastructure.