Politics · South Korea · 8 hrs ago
Gimhae faces rising costs as cross-river road remains unfinished
A planned four-lane road will link Gimhae and Busan across the Nakdong River in South Korea.
The project was agreed in 2003 and divided into two sections: Busan’s section opened in 2012, but Gimhae’s section only began construction in 2022.
Delays and rising prices have pushed the total cost from 117 billion won to 312.4 billion won.
Gimhae is paying a larger share because the government applied a 25% subsidy rate to its section, compared with 50% for the first section.
The city has borrowed to cover its costs, and the road spending has delayed other local road projects.
The unfinished section is due to open in September 2027, while provincial lawmakers seek a higher government subsidy; the provincial assembly will consider their motion by December 15.
The unfinished Chojung-Hwamyeong road has pushed Gimhae into borrowing as construction costs have risen sharply.
The 3.5-kilometer road is intended to connect Gimhae in South Gyeongsang Province with Busan across the Nakdong River.
Busan’s 2-kilometer section opened in 2012, but Gimhae’s 1.5-kilometer section did not begin in earnest until September 2022.
The total project cost has increased from 117 billion won to 312.4 billion won, and Gimhae’s share of costs is the largest among the local governments.
Thirty-two South Gyeongsang provincial lawmakers have proposed urging the government to increase national funding for Gimhae’s section.
- Who
- Gimhae and Busan are responsible for building the road. South Gyeongsang provincial lawmakers are calling for more national funding.
- What
- A cross-river road project remains unfinished, with rising costs placing a heavy financial burden on Gimhae.
- When
- The agreement was made in December 2003. Gimhae’s section is targeted for completion in September 2027.
- Where
- The road is to link Chojung-ri in Gimhae’s Daedong-myeon with Hwamyeong-dong in Busan’s Buk-gu, across the Nakdong River.
- Why
- Delays and rising prices increased the project cost, while national funding for Gimhae’s section was set at 25% for costs above 2 trillion won.
Gimhae and South Gyeongsang provincial lawmakers
The government
National funding rate
Gimhae and South Gyeongsang provincial lawmakers
Lawmakers say applying a 50% rate to the first section and 25% to the later section creates a serious fairness problem.
The government
Government guidelines provide 50% funding up to a total project cost of 2 trillion won and 25% for costs above that amount.
Requested action
Gimhae and South Gyeongsang provincial lawmakers
Lawmakers want the 50% rate applied to Gimhae’s section and reimbursement for costs Gimhae has already covered.
The government
Not stated
Gimhae and Busan agreed to build the Chojung-Hwamyeong metropolitan road.
Construction began on Busan’s Anmak-Hwamyeong section.
Busan’s 2-kilometer section opened.
Work on Gimhae’s Chojung-Anmak section began in earnest.
Thirty-two provincial lawmakers proposed a motion calling for increased national funding.
Gimhae’s section is targeted for completion.
- Total road length
- 3.5 kilometers
- Busan section
- 2 kilometers; opened in 2012
- Gimhae section
- 1.5 kilometers; targeted for completion in September 2027
- Total project cost
- 3,124 billion won, up from 1,170 billion won
- Gimhae local-government contribution
- 1,074 billion won
- Gimhae borrowing for the project
- 327 billion won, including borrowing planned through 2027
1 source
What people are saying
A serious fairness problem has arisen because a 50% national subsidy rate was applied to the first section of a single metropolitan road project, while a 25% rate was applied to the later section.
The structure that demands only Gimhae's sacrifice must be changed.
The government should apply a 50% national subsidy rate to the second-stage project and reimburse the costs Gimhae has already borne.