Gimhae faces rising costs as cross-river road remains unfinished

Gimhae faces rising costs as cross-river road remains unfinished

A planned four-lane road will link Gimhae and Busan across the Nakdong River in South Korea.

The project was agreed in 2003 and divided into two sections: Busan’s section opened in 2012, but Gimhae’s section only began construction in 2022.

Delays and rising prices have pushed the total cost from 117 billion won to 312.4 billion won.

Gimhae is paying a larger share because the government applied a 25% subsidy rate to its section, compared with 50% for the first section.

The city has borrowed to cover its costs, and the road spending has delayed other local road projects.

The unfinished section is due to open in September 2027, while provincial lawmakers seek a higher government subsidy; the provincial assembly will consider their motion by December 15.

1 source

Related

What people are saying

South Gyeongsang provincial lawmakersMembers of the provincial assembly
A serious fairness problem has arisen because a 50% national subsidy rate was applied to the first section of a single metropolitan road project, while a 25% rate was applied to the later section.
via Yonhap
The structure that demands only Gimhae's sacrifice must be changed.
via Yonhap
The government should apply a 50% national subsidy rate to the second-stage project and reimburse the costs Gimhae has already borne.
via Yonhap