Science & Tech · Science & Environment · 36 mins ago
Dutch data centers used 5% of the country’s electricity in 2025
Dutch data centers used an estimated 5% of the country's electricity in 2025, up from 4.6% in 2024.
The figures come from Statistics Netherlands, and the estimate for 2025 could still be revised.
Since measurement began in 2017, data centers' electricity use has nearly tripled.
The country has about 200 data centers, and around 50 large ones account for more than 90% of the electricity supplied to them.
Their servers run software and provide computing power for uses such as artificial intelligence, while cooling those servers also uses electricity.
With the power grid full in many places, new electricity connections are difficult to secure.
A national ban introduced in 2022 blocks construction of large data centers, but some projects with existing permits can still go ahead.
Dutch data centers used an estimated 5% of the country’s total electricity in 2025, up from 4.6% in 2024.
The figure is provisional and may be revised.
Since the national statistics agency began measuring in 2017, data center electricity use has almost tripled.
About 200 data centers operate in the Netherlands, and roughly 50 are classed as large.
Residents opposing a planned data center in Amsterdam say it would take too much electricity and drinking water and hinder housing construction.
- Who
- Data centers in the Netherlands.
- What
- They accounted for an estimated 5% of the country’s electricity use in 2025, up from 4.6% in 2024.
- When
- 2025; the figures were reported on November 18, 2026.
- Where
- The Netherlands.
- Why
- Data centers use electricity to run servers and cooling systems. The sources also say servers provide computing capacity for programs and artificial intelligence.
Amsterdam data center opponents
Company behind the planned Amsterdam data center
Utilities and housing
Amsterdam data center opponents
Residents say the data center would take too much drinking water and electricity, and opponents say it would hinder housing construction.
Company behind the planned Amsterdam data center
The company says the server capacity will be used by businesses and the government and will contribute to the economy.
Housing construction
Amsterdam data center opponents
Opponents say the data center stands in the way of housing.
Company behind the planned Amsterdam data center
Grid operator Liander denies that the data center blocks housing construction.
Statistics Netherlands began measuring data center electricity use.
The Rutte IV cabinet imposed a nationwide ban on building large data centers because electricity grid capacity was scarce.
Residents held a large protest against the planned data center in Amsterdam.
Data centers accounted for 4.6% of total Dutch electricity use.
Data centers accounted for an estimated 5% of total Dutch electricity use.
The figures were reported, with the 2025 estimate still subject to revision.
- Share of electricity in 2025
- 5% of total Dutch electricity use, provisional
- Share of electricity in 2024
- 4.6%
- Data centers in the Netherlands
- About 200
- Large data centers
- About 50; each uses more than 10 GWh annually
- Electricity supplied to data centers
- Large data centers use more than 90% of it
- EU comparison
- Only Ireland has a higher share of electricity use going to data centers