Business · Energy & Commodities · 53 mins ago
Battery storage plan proposed for Rivals filming estate in Wiltshire
Grenergy has proposed a large battery storage facility at Neston Park Estate near Corsham in Wiltshire.
The estate, which spans about 2,000 acres, is also the setting for Lord Tony Baddingham’s home in the TV drama Rivals.
The plans include a 450MW battery system and two water tanks, and would keep the facility on the land for 35 years before removing it.
Grenergy says the system would store surplus renewable electricity and release it when demand is high.
More than 800 objections have been submitted to Wiltshire Council, with residents raising concerns about the project’s scale and possible fire risks from lithium-ion batteries.
Some residents also say the development would be out of place on agricultural land near woodland.
Wiltshire Council is considering the application, which has been modified as it has gone through the planning process.
Grenergy has proposed a 450MW battery storage system on the Neston Park Estate in Wiltshire, where the television drama Rivals was filmed.
The plan, submitted to Wiltshire Council, also includes two 120,000-litre water tanks and would operate for 35 years.
More than 800 objections have been made, with residents raising concerns about the project’s scale and the potential fire hazard from large lithium-ion batteries.
Grenergy says the system would store surplus renewable electricity and release it when demand is high.
- Who
- Spanish renewable company Grenergy proposed the scheme. Residents including Geoff Fry and Joe Exon have objected.
- What
- A proposed 450MW battery energy storage system and two water tanks on Neston Park Estate.
- When
- The application was submitted many months before the article was published on 20 November 2026. The exact submission date is not stated.
- Where
- Neston Park Estate, near Corsham in Wiltshire.
- Why
- Grenergy says the system would store surplus renewable electricity and release it when demand is high. Residents cite the project’s scale, safety and environmental impacts.
Grenergy
Objecting residents
Purpose
Grenergy
Grenergy says the system is needed to store surplus renewable electricity and release it when demand is high.
Objecting residents
Residents argue the proposal offers no green benefit and would put a large industrial-scale development on agricultural land.
Safety and setting
Grenergy
Grenergy’s stated purpose is to store and release electricity.
Objecting residents
Residents raise concerns about fire risks from large lithium-ion batteries and the site’s proximity to woodland.
Grenergy submitted its application to Wiltshire Council; the exact date is not stated.
More than 800 objections had been made against the proposed site.
- Proposed capacity
- 450MW
- Water tanks
- Two, each 120,000 litres
- Proposed operating period
- 35 years
- Objections
- More than 800
- Estate size
- Approximately 2,000 acres
1 source
What people are saying
This is greenbelt land. It's adjacent to woodland. The woodland is the home for quite a large amount of fauna and flora.
The whole community understands that we need green energy but this isn't green energy.
So there is no green benefit to this.