US utilities demand proof before connecting data centers to the grid

US utilities demand proof before connecting data centers to the grid

US utilities are asking data center developers to prove their projects are real before committing to supply them with electricity.

Developers have requested 1,066 gigawatts of grid connections, but Wood Mackenzie expects utilities to commit to serving only about 28% of that demand.

Some requests are duplicated across utilities, while other projects may lack a confirmed site or customer.

Exelon’s high-probability data center load fell from 18 gigawatts to about 11 gigawatts after it required developers to accept financial obligations.

Utilities want to avoid building costly power lines and substations for projects that never proceed, because grid costs are shared and could affect other customers’ bills.

The issue matters as grid capacity is tight: the PJM grid operator’s latest capacity auction missed its reliability target by 6.8 gigawatts.