Akkuyu Unit 1 begins final hot and cold tests before fuel loading
Akkuyu's first unit has begun hot and cold tests at the nuclear power plant being built by Russia's Rosatom in Turkey.
The tests come before nuclear fuel is loaded and the unit begins producing electricity.
Engineers will test equipment under operating conditions, including the reactor's pipes, electrical systems and safety controls.
The reactor core will contain fuel-bundle simulators, not real nuclear fuel, during this stage.
The tests check that the systems work safely before the unit moves closer to operation.
After the tests, equipment will be inspected and uranium fuel bundles will be loaded for the first time.
Turkey's regulator must approve startup operations based on the inspection results.
Akkuyu Nuclear Power Plant Unit 1 has begun hot and cold tests, the final stage before start-up and commissioning work.
The tests will check equipment in both reactor circuits under operating conditions before nuclear fuel is loaded.
The reactor will be heated, with coolant temperature and pressure raised to 285°C and 16.5 MPa.
Fuel bundle simulators, rather than nuclear fuel, will be in the reactor core during the tests.
After the tests, equipment will be inspected before uranium-containing fuel bundles are loaded, subject to permission from Turkey’s regulatory authority.
- Who
- Rosatom, which is building the Akkuyu Nuclear Power Plant, said the tests had begun. The work concerns Unit 1.
- What
- Hot and cold tests of the reactor plant have started. They will check equipment and systems before fuel loading.
- When
- The tests were reported on November 18, 2026.
- Where
- Akkuyu Nuclear Power Plant, Turkey.
- Why
- To verify that equipment and safety systems meet requirements and that the unit is technically ready for first criticality.
This story does not have two clearly opposing sides.
Fuel bundle simulators will be in the reactor core while equipment and systems are tested.
The reactor plant will be heated and coolant temperature and pressure will be raised to nominal parameters of 285°C and 16.5 MPa.
Main and auxiliary equipment will be inspected to confirm compliance with project requirements and readiness for first criticality.
Uranium-containing fuel bundles will be loaded for the first time, and Turkey’s regulatory authority will decide whether start-up operations can begin.
- Unit
- Akkuyu Nuclear Power Plant Unit 1
- Coolant temperature
- 285°C
- Coolant pressure
- 16.5 MPa
- Fuel during tests
- Fuel bundle simulators, not nuclear fuel
- Next fuel step
- Uranium-containing fuel bundles will be loaded after the tests and equipment inspection
What people are saying
This is a final control stage, a kind of 'final rehearsal' for all the plant's systems.
We need to make sure that the equipment works reliably and that the safety systems perform their functions fully.