Business · Companies · 2 hrs ago
BHP plans to double South Australian copper output by 2040
BHP plans to double copper output in South Australia by 2040, raising annual production from its regional operations to 650,000 metric tons.
The expansion is expected to cost $14.2 billion to $18.1 billion and would involve Olympic Dam, Carrapateena and Prominent Hill, as well as a discovery at Ankata.
BHP says consolidating operations, using block caving and extending processing could significantly cut operating costs.
Copper is important for electrification, and BHP expects the South Australian operations to provide around one third of its planned copper growth to 2035.
The company aims to produce 2 million tons of copper globally by the middle of the next decade.
BHP expects to make its final investment decision in the first half of next year.
BHP plans to double its South Australian copper production by 2040, to 650,000 metric tons a year.
The expansion is expected to cost between $14.2 billion and $18.1 billion.
BHP expects a final investment decision in the first half of 2027.
The company says Copper South Australia will deliver around one third of its global copper growth to 2035.
The operations include Olympic Dam, Carrapateena, Prominent Hill and the Ankata discovery.
- Who
- BHP, the world’s top copper miner.
- What
- It plans to double annual copper production from its South Australian operations to 650,000 metric tons.
- When
- By 2040. A final investment decision is due in the first half of 2027.
- Where
- South Australia, Australia.
- Why
- The plan would increase BHP’s copper production as it pursues a global target of 2 million tons by the middle of the next decade.
This story does not have two clearly opposing sides.
BHP made a discovery at Ankata, originally named Oak Dam.
BHP acquired the Carrapateena and Prominent Hill mines.
BHP announced plans to double South Australian copper production by 2040.
BHP expects to make a final investment decision on the plan.
- Target output
- 650,000 metric tons of copper a year
- Target date
- 2040
- Estimated investment
- $14.2 billion to $18.1 billion
- Final investment decision
- First half of 2027
- Operations
- Olympic Dam, Carrapateena and Prominent Hill mines, and the Ankata discovery