Science & Tech · Science & Environment · 6 hrs ago
Iceland commissions its first utility-scale wind farm
Iceland has commissioned its first utility-scale wind farm, Vaðölduver, in the country’s south.
The national power company, Landsvirkjun, brought the first 14 turbines online on September 15, 2026.
The completed farm will have 28 turbines and 120 megawatts of capacity, enough to power the equivalent of 90,000 Icelandic households, according to Landsvirkjun.
Wind power can help conserve water in hydropower reservoirs because the utility can use wind-generated electricity instead of drawing as much on stored water.
The seasons help: strong winter winds coincide with lower reservoir inflows, while summer glacial melt increases water availability as winds tend to weaken.
Landsvirkjun plans to install the remaining 14 turbines, with the whole wind farm expected to be operating by the end of 2027.
Landsvirkjun commissioned Vaðölduver, Iceland’s first utility-scale wind farm, on September 15, 2026.
The first 14 turbines are online, and another 14 are planned for a second phase.
Once complete, the wind farm will have 120 megawatts of capacity and is expected to operate fully by the end of 2027.
Vaðölduver connects to existing Búrfell hydropower infrastructure and can help conserve reservoir water when winds are strong.
Landsvirkjun sees wind as a potential third pillar of Iceland’s electricity supply, alongside hydropower and geothermal energy.
- Who
- Landsvirkjun, Iceland’s national power company, commissioned the wind farm.
- What
- Vaðölduver is Iceland’s first utility-scale wind farm. It is planned to have 120 megawatts of capacity.
- When
- It was commissioned on September 15, 2026. Full operation is expected by the end of 2027.
- Where
- On a lava-and-sand plain east of the Þjórsá River, south of Sultartangi Dam, Iceland.
- Why
- It adds wind generation and can help conserve hydropower reservoir water when winds are strong.
This story does not have two clearly opposing sides.
Landsvirkjun drew on a decade of experience operating pilot wind turbines.
Landsvirkjun officially commissioned Vaðölduver.
Landsvirkjun plans to install another 14 turbines.
The entire wind farm is expected to be operating.
- Commissioned
- September 15, 2026
- First phase
- 14 turbines online
- Second phase
- 14 more turbines planned
- Planned capacity
- 120 megawatts
- Expected full operation
- By the end of 2027