Indonesia plans to begin work on a giant sea wall in 2027 along Java’s north coast.
The first construction starts are planned for Jakarta Bay and Semarang Bay, including areas around Kendal, Semarang, Demak and Sayung.
The government has divided the proposed project into 15 segments, and the two bays are among them.
Officials say land sinking and tidal floods make these areas a priority.
The Jakarta Bay plan includes a 42.82-kilometre sea wall, a reservoir of about 7,000 hectares and links to other infrastructure.
Plans for sections there also include artificial islands, a bridge, solar panels and mangrove areas.
Officials say technical designs are ready for Semarang Bay, and the next step is to start construction in the planned locations in 2027.
Indonesia plans to begin construction of a giant sea wall along Java’s northern coast in 2027.
The first work is planned for Jakarta Bay and the Kendal-Semarang-Demak area.
Officials say the locations are priorities because of land subsidence and tidal flooding.
The government plans a sea wall of about 575 kilometres, built in stages from Serang to Gresik.
The project is being designed with scientific studies of waves and soil, and is intended to last about 300 to 400 years.
- Who
- Indonesia’s government, through the North Java Coast Management Authority (BOPPJ).
- What
- It plans to begin construction of a giant sea wall along Java’s northern coast.
- When
- Work is planned to start in 2027.
- Where
- The first sections are planned for Jakarta Bay and Kendal-Semarang-Demak; the wider project is planned from Serang to Gresik.
- Why
- Officials cite land subsidence and tidal flooding along the coast, and say the project is intended to protect coastal areas.
This story does not have two clearly opposing sides.
BOPPJ head Didit Herdiawan Ashaf discussed the project at a hearing with Commission IV of Indonesia’s House of Representatives.
The government plans to begin construction in Jakarta Bay and the Kendal-Semarang-Demak area.
- Planned start
- 2027
- Total planned length
- About 575 kilometres
- First locations
- Jakarta Bay and Kendal-Semarang-Demak
- Jakarta Bay sea wall length
- 42.82 kilometres
- BOPPJ 2027 budget allocation
- Rp 481.1 billion
3 sources
What people are saying
This is a priority. If we do not intervene, submergence will occur in a short time.
We hope that once this project is built, it will last about 300 to 400 years.