Business · Energy & Commodities · 20 hrs ago

Chicoasén II hydroelectric plant in Chiapas is 51.35% complete

Chicoasén II hydroelectric plant in Chiapas is 51.35% complete

Claudia Sheinbaum visited the Chicoasén II plant under construction in Chiapas, Mexico, on November 8.

The project is 51.35% complete, according to the Federal Electricity Commission, or CFE.

Chicoasén II will use water discharged from the existing Manuel Moreno Torres hydroelectric plant, as well as natural flows from the Grijalva River.

The new plant is planned to add 240 megawatts to Mexico’s electricity system, using turbines designed for lower water pressure.

The CFE estimates its output could benefit 54,241 additional households.

The project also includes a 400-kilovolt substation, transmission links and 250 million pesos in social and local development works.

The CFE has not given a completion date in the information provided.