Mexico City Cablebús Line 4 construction advances at Universidad terminal
Construction is advancing on Mexico City’s Cablebús Line 4, the fourth line of the city’s electric cable-car system.
The Universidad terminal is being built next to the Metro Line 3 station by Ciudad Universitaria, where passengers will be able to connect between the services.
The planned line will be 11.4 kilometres long with nine stations and is intended to serve residents of 44 neighbourhoods.
Work at Universidad includes foundations and the construction of 28 support columns, while nearby bus stops and walking routes have been changed during construction.
Equipment for the system is being made in Italy and is 63% complete, according to the city’s public works department.
The next construction stages include further foundations and support structures, and the project is expected to be completed in December 2027.
Construction of Mexico City Cablebús Line 4 is advancing at the Universidad terminal, where support columns are visible.
The terminal is beside Universidad station on Metro Line 3, outside Ciudad Universitaria.
The works include foundation work and the construction of 28 columns for the station.
Line 4 is planned to run 11.4 kilometres, with nine stations linking Universidad and Pedregal de San Nicolás.
The project is scheduled for completion in December 2027.
- Who
- Mexico City’s Secretariat of Works and Services is overseeing the construction.
- What
- Construction of the Universidad terminal for Cablebús Line 4 is progressing.
- When
- The article was published on November 19, 2026; a construction start date is not stated.
- Where
- Beside Universidad station on Metro Line 3, outside Ciudad Universitaria in Mexico City.
- Why
- The route aims to make transfers easier and serve residents in the south of Mexico City.
This story does not have two clearly opposing sides.
The Mexico City government launched the project to build Cablebús Line 4.
Technical and architectural studies for the Universidad terminal were completed.
The Secretariat of Works and Services shared images showing construction progress, including visible columns.
The project is scheduled for completion.
- Terminal
- Universidad, beside Metro Line 3
- Station columns
- 28
- Route length
- 11.4 kilometres
- Number of stations
- 9
- Planned completion
- December 2027