Business · Companies · 49 mins ago

Adani rejects claim it cut Tarali project cost to reduce obligations

Adani rejects claim it cut Tarali project cost to reduce obligations

Adani Group says the lower figure was only for site surveys for its Tarali pumped-storage project in Maharashtra.

The 1,500-megawatt project’s full cost was set at ₹5,675 crore, while the online clearance proposal listed ₹56.75 crore.

A report said the revised figure could reduce a required wildlife conservation contribution from ₹227 crore to about ₹2.27 crore.

The group denies it cut the project cost to lower that contribution, saying the survey costs were about 1% of the full project cost.

It says the project is on private, non-forest land and does not affect protected areas or wildlife corridors.

The Union environment ministry directed a state investigation after a complaint alleging the project cost was incorrectly stated.

The Congress has called for a parliamentary committee probe, while the state forest department has begun investigating.

3 sources

Related

What people are saying

Adani Group spokespersonGroup spokesperson
Since site investigation costs are around 1 per cent of project costs, therefore, clarification of the project, Rs 56.75 crore, representing solely the site investigations and survey costs, for the online proposal was provided
via Economic Times
Jairam RameshCongress general secretary in-charge communications
It points to a scandal of gigantic proportions, reinforcing the demand for a JPC into its operations
via The Hindu
Modani has slashed its project cost for a 1500 MW pumped storage power project in Maharashtra. A project which was sanctioned last year for ₹5,675 crore is now stated in an affidavit to have a cost of ₹56.75 crore. It is a 99% reduction!