Seoul mayor accuses heritage agency of delaying Jongmyo-area redevelopment
Seoul Mayor Oh Se-hoon accused the national heritage agency of obstructing redevelopment in Seun 4, a district near Jongmyo shrine in Seoul.
The agency has requested a World Heritage impact assessment and postponed buried-heritage reviews four times, according to Oh.
The project received approval in June, but Oh says the agency changed rules while administrative procedures were under way and lacks grounds to demand that the approval be cancelled.
The heritage agency’s position is not included in the account.
Residents are paying more than 1.4 billion won in monthly interest and have filed a damages lawsuit against the state seeking more than 25 billion won, Oh said.
He argues that development can coexist with protecting Jongmyo and disputes claims that the plan would harm the shrine.
Oh wants the rules revised so redevelopment is not unfairly delayed, including around the Hanyang City Wall, which faces a World Heritage listing review next year.
The Seun 4 project’s next buried-heritage review will be its fifth.
Seoul Mayor Oh Se-hoon accused the Korea Heritage Service of delaying redevelopment in the Se운 4 district near Jongmyo Shrine.
Oh said the agency changed regulations during the approval process and repeatedly deferred reviews, despite the project receiving approval in June.
He argued that the district lies outside Jongmyo’s World Heritage zone and that the agency lacks legal grounds to demand a heritage impact assessment or cancel the approval.
The agency has requested a heritage impact assessment and deferred buried-heritage reviews four times, according to Oh.
Oh called for changes to the regulations and said he would oppose delays to other redevelopment projects near the Seoul City Wall.
- Who
- Seoul Mayor Oh Se-hoon accused the Korea Heritage Service of obstructing redevelopment.
- What
- Oh said the agency had delayed the Se운 4 district project near Jongmyo Shrine through regulatory changes and repeated review deferrals.
- When
- November 18, 2026.
- Where
- Se운 4 district, near Jongmyo Shrine in Seoul.
- Why
- Oh said the agency’s demands lack a legal basis and interfere with local permitting authority.
Oh Se-hoon
Korea Heritage Service
Legal basis
Oh Se-hoon
Oh said the agency lacks legal grounds to require an assessment or seek cancellation of the approved project.
Korea Heritage Service
Not stated in the article.
Project reviews
Oh Se-hoon
Oh said the agency’s heritage impact assessment request and four buried-heritage review deferrals are delaying the project.
Korea Heritage Service
The agency requested an impact assessment and deferred the reviews four times; its reasons are not detailed in the article.
The Se운 4 district project received approval, according to Oh.
The Korea Heritage Service had requested a heritage impact assessment and deferred buried-heritage reviews four times, Oh said.
Oh accused the agency of delaying the project during questioning at the Seoul Metropolitan Council.
- Project area
- Se운 4 district, near Jongmyo Shrine
- Project approval
- June 2026
- Buried-heritage reviews deferred
- Four times
- Residents’ monthly interest costs
- More than 1.4 billion won, according to Oh
- Residents’ damages lawsuit
- More than 25 billion won against the state, according to Oh
1 source
What people are saying
This is effectively legislation after the fact and an administrative abuse.
Jongmyo preservation and development can coexist.
Let us go to the site and see together whether that height significantly damages the view of Jongmyo.