China’s grid uses rapid protection systems to limit power faults
China’s power grid supplied more than 10.4 trillion kilowatt-hours in 2025, while users averaged 6.04 hours without power over the year.
The network relies on many technologies, including relay protection, which monitors current and voltage for signs of trouble.
When it detects a fault, relay protection can identify the problem in under 10 milliseconds and disconnect the affected section so other parts can keep working.
In the 1980s, China relied heavily on imported protection equipment, which was costly.
Guo Rong Shen and his team developed domestic systems, and equipment for 500-kilovolt lines sold for far less than imported alternatives.
The grid also has three layers of protection: cutting off faults, balancing electricity supply and demand, and separating parts of the network in extreme cases.
Most faults are resolved by the first layer, while the third is rarely used.
China plans to expand its “west-to-east power transmission” capacity to more than 420 million kilowatts by 2030, while continuing to improve grid intelligence and flexibility.
China’s grid uses relay protection systems that can identify faults in under 10 milliseconds and disconnect the affected section while keeping the rest of the grid running.
A three-layer defence system also helps balance supply and demand and isolate parts of the grid in extreme conditions.
China’s average power outage time per user was 6.04 hours in 2025, according to a report cited by China News Service.
The article traces the development of the protection technology from research led by Shen Guorong and describes the growth of domestic equipment production.
China’s ultra-high-voltage network includes 45 transmission corridors and more than 60,000 kilometres of lines.
- Who
- China’s power grid and the researchers and engineers who developed its protection systems.
- What
- Rapid relay protection detects faults and cuts off affected sections; a three-layer system provides further safeguards.
- When
- The article describes developments from 1981 onward and reports grid figures for 2025.
- Where
- China.
- Why
- To limit power faults and maintain stable electricity supply.
This story does not have two clearly opposing sides.
Shen Guorong proposed the power-frequency variation relay protection principle, which reduced fault detection time to under 10 milliseconds.
Shen led a team that turned the principle into equipment and put domestic relay protection devices on the market.
The impedance sequential-discrimination out-of-step relay received a National Invention Award, the first such award in the power industry.
Fast directional protection based on power-frequency variation received a National Invention Award.
Shen led the construction of China’s first automated relay-protection production line designed for small-batch, varied production.
China’s average power outage time per user was 6.04 hours, and total electricity consumption reached 10.4 trillion kilowatt-hours.
- Fault detection
- Under 10 milliseconds
- Average outage time per user
- 6.04 hours in 2025
- Electricity consumption
- More than 10.4 trillion kilowatt-hours in 2025
- Ultra-high-voltage corridors
- 45
- Ultra-high-voltage transmission lines
- More than 60,000 kilometres
1 source
What people are saying
These two significant awards reflect the process by which a generation of relay protection technology gradually became a system and came to lead the world.
The technology had to be developed by us. For the first demonstration project, we had to lead the technology ourselves.