Trans Mountain completes pipeline project to boost flows ahead of schedule
Trans Mountain Corp.
has completed a project to increase pipeline flows two months ahead of schedule.
The work affects its pipeline carrying crude oil from Alberta to British Columbia.
Chemical additives reduce drag inside the pipeline, allowing more oil to move through without building new pipeline segments for this project.
The change raises capacity by about 10 per cent, to 980,000 barrels a day.
That gives the pipeline more room to carry crude oil.
A separate expansion of 210,000 barrels a day is expected by the end of 2028, using new pipeline sections and pump stations.
Trans Mountain Corp. says it has completed a project to increase crude flows on its Alberta-to-B.C. pipeline two months ahead of schedule.
The project uses chemical additives that increase the pipeline’s capacity by about 10 per cent, to 980,000 barrels per day.
A further expansion of 210,000 barrels per day, using new pipeline segments and pump stations, is expected to enter service by the end of 2028.
In the third quarter, the pipeline shipped an average of 840,000 barrels per day, up from 777,000 barrels per day in the same period of 2025.
- Who
- Trans Mountain Corp., the Crown corporation that operates the pipeline.
- What
- It completed a project using chemical additives to increase pipeline capacity by about 10 per cent.
- When
- The completion was reported on Nov. 27, 2026, two months ahead of schedule.
- Where
- On Trans Mountain’s Alberta-to-B.C. pipeline.
- Why
- To increase the amount of crude that can flow through the pipeline.
This story does not have two clearly opposing sides.
The pipeline shipped an average of 840,000 barrels per day, up from 777,000 barrels per day in the same period of 2025.
Trans Mountain Corp. reported that the capacity-increase project was complete, two months ahead of schedule.
A further expansion of 210,000 barrels per day is expected to enter service.
- Capacity increase
- About 10 per cent
- Pipeline capacity after project
- 980,000 barrels per day
- Further expansion
- 210,000 barrels per day
- Expected service date for further expansion
- By the end of 2028
- Third-quarter 2026 average shipments
- 840,000 barrels per day