Business · Companies · 5 hrs ago
ACS is favorite to build Oracle’s $4.5 billion Nashville headquarters
ACS and Archer Western are favorites to build Oracle’s new headquarters and AI campus in Nashville, Tennessee.
The Spanish construction company would work through its US unit Turner alongside Archer Western, which belongs to construction group Walsh.
Oracle plans to invest $4.5 billion in the complex, but the contract has not been officially awarded.
The campus is planned for the River North district, on a site of about 32 hectares, with offices, public spaces and other facilities.
The project is expected to create thousands of jobs and is part of a major urban redevelopment effort in Tennessee.
Oracle is expanding its cloud, digital infrastructure and AI operations, while Nashville also has a strong health sector that fits Oracle’s healthcare business.
Main construction is scheduled to start in November 2026, and the campus is expected to be operational in 2031.
ACS, through Turner and local partner Archer Western, is the favorite to build Oracle’s planned global headquarters and AI campus in Nashville.
Oracle expects to invest $4.5 billion in the complex.
The project has not been officially awarded.
The campus is planned for the River North district in Nashville’s East Bank area, beside the Cumberland River.
Main construction is scheduled to begin in November 2026, and the campus is expected to be operational in 2031.
- Who
- ACS, through Turner, and local partner Archer Western are favorites to build the campus for Oracle.
- What
- A planned global headquarters and AI campus. The project has not been officially awarded.
- When
- Main construction is scheduled to begin in November 2026, with operations expected in 2031.
- Where
- River North, in Nashville’s East Bank area, beside the Cumberland River.
- Why
- Oracle aims to expand in cloud services, digital infrastructure and artificial intelligence, and to concentrate technology talent and strengthen its operations.
This story does not have two clearly opposing sides.
Main construction is scheduled to begin.
The campus is expected to be operational.
- Investment
- $4.5 billion
- Location
- River North, Nashville, Tennessee
- Site area
- About 32 hectares
- Estimated built area
- About 186,000 square metres
- Planned opening
- 2031