Business · Energy & Commodities · 2 hrs ago

US Builds About 10% of the Power Lines Needed to Meet Demand

US Builds About 10% of the Power Lines Needed to Meet Demand

The US built about 500 miles of high-voltage lines a year over the past five years, while researchers say it needs 5,000 miles a year to expand the grid by 2050.

Demand for electricity is rising with the growth of AI and data centers, industry and electrification.

Researchers from Carnegie Mellon University and the University of California San Diego say the main obstacle is fragmented approval processes involving states, local authorities and utilities.

They say this grid bottleneck could weaken grid resilience, economic competitiveness and energy affordability.

Their proposals include making better use of existing rules and technology, testing new approaches and creating a presidential-congressional commission to develop a new framework.

Separately, Johns Hopkins researchers warn that shortages of grid equipment and materials could begin as early as next year, with acute shortages by 2030.

The proposals aim to make it easier to build transmission lines, but the sources do not say whether officials will adopt them.

1 source

Related

What people are saying

David G. VictorUC San Diego researcher
As it stands, we have a system with lots of veto points and weak incentives to build the projects that deliver the greatest value across regions
via OilPrice
Utilities are generally rewarded for investments inside their own service territories. Once a line crosses utility or state boundaries, more players get involved, approvals become more complicated, and fights break out over who pays and who benefits.
via OilPrice
Yury DvorkinJohns Hopkins study author
When the demand for electricity started to grow faster than expected, it started to amplify all the cracks in the industry
via OilPrice
Jason TofskyGlobal head of Digital Infrastructure Investment Banking at Goldman Sachs
Power is probably the forever bottleneck
via OilPrice