NextDC shares plunge 40% after power delays force guidance cut

NextDC shares plunge 40% after power delays force guidance cut

Australian data centre operator NextDC cut its outlook after power delays at its M3 facility in West Footscray, Melbourne.

The company said delays in getting electricity to the site affected its guidance, but the sources do not give the revised figures.

NextDC’s shares fell 40% after the guidance cut as the Australian market opened higher.

The M3 site is being expanded, and its power connection requires high-voltage lines through nearby residential streets.

A local protest halted work on part of the power-line project, though neither NextDC nor electricity distributor Jemena confirmed that this caused the delay.

The setback highlights grid constraints and local opposition to data centres as Australia’s demand for power-hungry AI infrastructure grows.

NextDC had sought a trading halt while assessing the delay, and said it would remain in place until Wednesday or until the company made a full announcement.