Some renewable energy projects in India have been built or planned but do not yet have buyers for their electricity.

About 42 GW of renewable capacity is waiting for power purchase agreements.

Distribution companies are finding some hybrid projects too expensive.

They are also having difficulty buying regular solar power from some projects.

Developers are adding batteries to solar plants so the electricity can be supplied more reliably.

Some developers may choose to leave these projects without losing certain bank guarantees.

Wind projects are being bought more actively than some solar projects.

India also wants to make more polysilicon, an important material for solar panels, inside the country.

Officials are also looking at batteries made with sodium and vanadium as alternatives to lithium-ion batteries.