Archive · 11 Jan 2026
RECPDCL Transfers Two Maharashtra Transmission Projects
On January 9, 2026, RECPDCL, a company under the Ministry of Power, gave two important power line projects in Maharashtra to two different companies.
One project, called Velgaon Power Transmission, was given to Ceigall India Limited.
This project involves building a big power station and some power lines.
The other project, called Jejuri Hinjewadi Power Transmission, was given to The Tata Power Company Limited.
This project involves building a long power line.
Both projects will take 24 months to complete.
These projects are part of efforts to make sure power can be moved around Maharashtra reliably and efficiently.
RECPDCL handed over two Intra-State Transmission Project SPVs in Maharashtra on 09th January 2026.
Velgaon Power Transmission Limited was transferred to Ceigall India Limited for a 400/220 kV substation and associated lines.
Jejuri Hinjewadi Power Transmission Limited was transferred to The Tata Power Company Limited for a 400 kV transmission line.
Both projects were awarded through the Tariff-Based Competitive Bidding (TBCB) process and will take 24 months to implement.
The handover was conducted in the presence of senior officials from RECPDCL, the winning companies, and Maharashtra STU.
- Who
- RECPDCL, Ceigall India Limited, The Tata Power Company Limited
- What
- Handover of two Intra-State Transmission Project SPVs in Maharashtra
- When
- 09th January 2026
- Where
- Maharashtra, India
- Why
- To strengthen transmission infrastructure through competitive bidding
- Date
- 09th January 2026
- Companies Involved
- Ceigall India Limited, The Tata Power Company Limited
- Project Types
- Intra-State Transmission Projects
- Implementation Period
- 24 months for both projects
- Bid Process
- Tariff-Based Competitive Bidding (TBCB)
- Project 1 Details
- 400/220 kV Velgaon Substation (GIS) and LILO of 400 kV and 220 kV lines
- Project 2 Details
- 400 kV Double Circuit transmission line of 115 km from Jejuri to Hinjewadi