Karimnagar Completes RTFMS Integration Across All 82 Substations

Karimnagar Completes RTFMS Integration Across All 82 Substations
Karimnagar Circle of TG NPDCL Leads in Real-Time Power Supply Monitoring · deccanchronicle.com

Karimnagar is the first circle in TG NPDCL to connect all of its 82 substations to a system called RTFMS.

The substations are linked to SCADA, which lets officials monitor electricity feeders from a control room.

The system can alert staff when power stops, a feeder is overloaded, or voltage changes.

Officials say this helps workers find problems and respond faster.

So far, 1,005 of the 1,424 substations identified across the network have been connected.

The remaining 419 are expected to be connected within two months.

The utility says other circles are also close to completing the work.

Its stated goal is to improve the reliability of electricity supply.

Key facts

Karimnagar integration
82 of 82 substations
Integrated across TG NPDCL
1,005 substations
Total identified for integration
1,424 substations
Remaining substations
419
Expected completion for remaining integration
Within the next two months
Circles expected to complete integration soon
Hanamkonda, Khammam and Kumaram Bheem Asifabad
Monitoring setup