Noida Homebuyer Wins Compensation After Seven-Year Flat Delay

Noida Homebuyer Wins Compensation After Seven-Year Flat Delay

Shyam Sunder Agrawal bought a home in Noida in 2010.

The builder said the home would be ready by 2012.

Instead, Agrawal received it in March 2017.

During the wait, his family rented another home and he continued paying his loan.

He said the flat was still missing important paperwork when it was handed over.

He asked for money to make up for the long delay.

A tribunal supported his claim, and the Allahabad High Court later agreed.

The court said accepting the home did not erase his right to compensation.

The builder argued that environmental restrictions caused the delay, but the court did not accept that explanation for the relevant period.