Supreme Court Orders Developer to Refund with Enhanced Interest
The Supreme Court told a Delhi developer to give back over Rs 43 lakh to a person who bought a plot.
The court increased the interest rate to 18% because the developer took a long time to give the plot.
The buyer, Rajnesh Sharma, paid for the plot in 2006 but never received it.
The court decided that the initial 9% interest from the lower court was not fair.
The developer had charged 18% interest on the delayed payment from the buyer and the buyer had waited for a decade.
The developer has two months to return the money.
The Supreme Court ordered a Delhi developer to refund over Rs 43 lakhs to a plot purchaser.
The refund includes an 18% interest rate.
The interest rate was increased from 9% to 18% per annum.
The court criticized the developer's conduct, citing delays and unfair penalties.
The case involved a plot booked in 2006 by Rajnesh Sharma.
- Who
- Supreme Court, M/s Business Park Town Planners Ltd., and Rajnesh Sharma
- What
- Ordered a Delhi-based developer to refund over Rs 43 lakhs to a plot purchaser with 18% interest.
- When
- The case began in 2006.
- Where
- Delhi, Supreme Court
- Why
- Due to the developer's prolonged delays, unfair penalties, and a decade-long wait causing harassment and anxiety.
- Developer
- M/s Business Park Town Planners Ltd.
- Plot Purchaser
- Rajnesh Sharma
- Initial Investment
- Rs 36,03,692
- Total Repayment
- Over Rs 43 lakh
- Interest Rate
- 18% per annum
- Previous Interest Rate
- 9% per annum
- Court
- Supreme Court