Archive · 4 Sep 2026

Officials Set Two-Month Deadline for Raptadu Water Projects

Officials Set Two-Month Deadline for Raptadu Water Projects

Officials checked how much work has been completed on village drinking-water projects.

The projects cover Atmakuru, Anantapur Rural and Raptadu mandals.

Two companies are building pipelines, tanks, filters and pumping systems.

Much of the work is still unfinished.

The officials said the remaining work must be completed within two months.

The goal is to provide water to 30 villages.

They ordered new sand filters and faster purchase of pumps.

They also asked for quicker approvals and the handover of land needed for construction.

The review was held because villages are facing water stress.

Sources