Budameru Canal Breach Repaired with New Concrete Wall
The Budameru canal, which had a broken section, has been fixed with a new wall built quickly.
The minister in charge announced the completion.
The left side of the canal was also made stronger.
New gates were added to help control water flow.
Other work is planned, like making the canal bigger and cleaning it out, to prevent flooding and help water move more freely to the sea.
A new 365-meter concrete wall has been constructed to plug the Budameru canal breach.
Construction began after tenders were called in May.
The canal's left bank was strengthened by raising its height.
12 new gates were set up at the Velagaleru regulator.
Desilting and capacity increase works are planned for the canal and related infrastructure.
- Who
- Water resources minister Nimmala Ramanaidu.
- What
- A breach in the Budameru canal was repaired, and other related infrastructure work is underway.
- When
- Construction of the wall started after tenders in May.
- Where
- Budameru canal and related areas.
- Why
- To repair the canal breach, prevent flooding, and improve water flow.
- Canal Breach Repair
- 365-meter concrete wall
- Left Bank Improvement
- Height raised by half a meter for 7 km
- Velagaleru Regulator
- 12 new gates installed
- Desilting Length
- 57 km of Budameru canal
- Old Canal Capacity Increase
- From 4,000 cusecs to 20,000 cusecs