Stone-Pelting During Indore RE-2 Clearance Drive Injures Two

Stone-Pelting During Indore RE-2 Clearance Drive Injures Two
Stones Fly As Indore’s RE-2 Clearance Begins In Kanadia; 2 Injured, 8-9 Detained · freepressjournal.in

Officials in Indore began clearing buildings that stand in the way of finishing a road called RE-2.

The work took place in parts of Kanadia on Tuesday.

Some people opposed the action, and stones were thrown as the machines were leaving, according to officials.

Two people were hurt, and police detained about eight or nine people.

Officials said they first spoke with residents and that some people moved their belongings.

The road is 4.25 kilometres long, but nearly one kilometre is still unfinished.

Authorities say many affected families have already moved to other homes.

They plan to shift more families to housing at Nilgiri.

Key facts

RE-2 length
4.25 kilometres
RE-2 width
45 metres
Completed
Around 3.20 kilometres
Unfinished
Nearly one kilometre, which the article says has remained unfinished for about three years
Project spending
Around Rs 55 crore
Families rehabilitated
325; 303 have shifted to housing units, while 22 houses remained due to a court stay
People affected in incident
Two injured; around eight to nine detained, according to officials