Archive · 11 Sep 2026
Sigma Advanced Systems starts aerospace production at Sri City
Sigma Advanced Systems has started making airplane parts at a new factory in Sri City, India.
The factory began production only eight months after construction started.
Its first parts were sent to the company’s UK operations for checking.
The facility currently has enough equipment for 100,000 machine-hours of work each year.
It may eventually grow to nearly 300,000 machine-hours per year.
Sigma wants to move more of its airplane-parts manufacturing to India.
After expansion, about 70% of the manufacturing process is expected to happen there.
The company also plans to train workers in specialised aerospace skills.
Sigma Advanced Systems has begun producing precision-machined aerospace components at its Sri City facility in Andhra Pradesh.
The facility moved from construction to active production in eight months, and its first batch was sent to the company’s UK operations for final verification.
The 75,000-square-foot facility currently supports 100,000 machining hours annually and is designed to scale up to nearly 300,000 hours.
Sigma expects about 70% of its aerospace manufacturing process to be carried out in India after the planned expansion.
The facility has completed initial source-change approval stages with Rolls-Royce Aerospace and plans to provide specialised on-campus training.
- Who
- UK-based Sigma Advanced Systems, led by CEO and Executive Director Sunil Kalidindi.
- What
- The company has begun aerospace component production and sent its first batch to its UK operations for final verification.
- When
- Production began after the facility moved from construction to operation in eight months; the remaining campus is expected to become operational over the next 12 months.
- Where
- Sri City in Andhra Pradesh; the reports describe the location differently, with one referring to Nellore and another to the Tirupati area.
- Why
- To replicate Sigma’s UK aerospace manufacturing capabilities, expand production in India and shift a larger share of its manufacturing value chain to the country.
- Facility size
- 75,000 square feet, within a planned 500,000-square-foot campus
- Current capacity
- 100,000 machining hours annually
- Planned capacity
- Nearly 300,000 machining hours annually
- Expected India share
- Around 70% of the manufacturing process after expansion
- First production batch
- Sent to Sigma’s UK operations for final verification
- Approval progress
- Initial stages of the source-change approval process completed with Rolls-Royce Aerospace
- Expansion timeline
- The remaining portion of the campus is expected to become operational within 12 months