Oracle Seeks Payment Delay for Massive New Mexico AI Center

Oracle Seeks Payment Delay for Massive New Mexico AI Center
Oracle Invokes Force Majeure On Massive New Mexico AI Data Center Project · freepressjournal.in

Oracle is helping build a very large AI data center in New Mexico.

The center is called Project Jupiter and is supposed to open in 2028.

Oracle sent a legal notice saying it may need more time before paying rent if important construction work is delayed.

This does not mean Oracle is leaving the project.

If both sides agree that a power-related problem caused a delay, Oracle could postpone rent payments for up to three years.

The project needs a natural-gas pipeline, but that pipeline has been delayed.

Some local and political groups oppose the growth of large AI data centers.

Oracle and Blue Owl say they are still committed to the project.

Investors nevertheless worried, and shares of both companies fell.

Key facts

Project
Project Jupiter data center campus
Planned capacity
2.45 gigawatts
Planned opening
2028
Potential payment delay
Up to three years on rent, if an agreed force majeure event occurs
Pipeline delay
Nearly six months, with completion expected in February 2027
Construction financing
An $18 billion loan provided by about 20 banks
Market reaction
Oracle shares fell 4.4% in early trading and Blue Owl shares fell 3.7%