Bombay High Court Orders Kalpataru Lease Registration Without Penalty

Bombay High Court Orders Kalpataru Lease Registration Without Penalty

Kalpataru Gardens made a very long lease agreement for a plot in Bhandup in 2017.

The company gave the document to government officials so they could decide how much stamp duty was owed.

That process took several years because of appeals, revaluation and the Covid-19 pandemic.

The company later used an amnesty scheme and paid revised stamp duty in 2025.

Officials then refused to register the lease because it was submitted after the usual four-month deadline.

The company said it should not be punished because the government process had taken so long.

The Bombay High Court agreed with the company.

The court said the government-delay period should not count against Kalpataru.

It ordered registration without a penalty.