Archive · 18 Jan 2026
CG Power Secures $99.2M US Data Center Order
CG Power, a big engineering company, just got a huge order worth ₹900 crore from a company in the US.
They need to make special power transformers for a big data center.
This is the biggest order CG has ever gotten, and it's a really important deal because it's their first time working on a big data center project outside India.
They will make these transformers in their factories in India and send them to the US.
The company's boss said this shows that CG can make really good, reliable technology that people around the world can trust.
It will take them about 1 to 2 years to finish making and sending all the transformers.
CG Power secures ₹900 crore ($99.2M) order for US data center project.
This is the largest single order CG has ever won.
CG will supply power transformers for hyperscale data center applications.
Transformers will be designed, manufactured, and tested in India.
Delivery period is 12 to 20 months with delivery terms FAS Mumbai Port.
- Who
- CG Power and Industrial Solutions Limited (CG)
- What
- Secured an order for power transformers for a data center project
- When
- Order secured on January 17, 2026
- Where
- Project in the US, transformers manufactured in India
- Why
- To supply power transformers for a large-scale data center project
- Company
- CG Power and Industrial Solutions Limited (CG)
- Order Value
- ₹900 crore ($99.2M)
- Client
- Tallgrass Integrated Logistics Solutions LLC, US
- Project Type
- Large-scale data center project
- Products Supplied
- Power transformers
- Delivery Period
- 12 to 20 months
- Delivery Terms
- FAS Mumbai Port (Incoterms 2020)
- Manufacturing Location
- India