TG RERA Slaps ₹32 Lakh Penalty on Janapriya Projects
A couple booked a flat in a project run by Janapriya Projects.
The company accepted ₹2,44,608 before the project was registered with the real estate regulator.
The project was registered several months later.
Telangana’s real estate authority said this broke the rules.
It ordered the company to pay a penalty of ₹32,17,780.
The company must also finish the flat’s water and electricity connections.
It must give the couple a lawful, ready-to-move-in home and register the sale deed.
The couple will receive interest on their payments until the flat is handed over.
TG RERA held Janapriya Projects liable for collecting a booking advance before mandatory project registration.
The developer received ₹2,44,608 under an allotment letter dated March 30, 2019.
The Sitara at Janyapriya Lake Front project was registered with TG RERA on October 5, 2019.
The authority imposed a ₹32,17,780 penalty, payable to the TGRERA Fund within 30 days.
Janapriya Projects must complete pending works, hand over possession, register the sale deed, and pay interest to the complainants.
- Who
- The Telangana Real Estate Regulatory Authority, Janapriya Projects Pvt. Ltd., and a couple who booked a flat.
- What
- TG RERA imposed a ₹32,17,780 penalty for collecting a booking advance before project registration and ordered the developer to complete the flat and hand over possession.
- When
- The allotment letter was dated March 30, 2019; the project was registered on October 5, 2019; and interest is calculated from August 21, 2024.
- Where
- The case concerns the Sitara at Janyapriya Lake Front project in Telangana.
- Why
- The authority found that accepting an advance before obtaining mandatory RERA registration violated Section 3(1) of the Real Estate (Regulation and Development) Act, 2016.
- Penalty
- ₹32,17,780
- Amount collected
- ₹2,44,608
- Allotment date
- March 30, 2019
- RERA registration date
- October 5, 2019
- Payment deadline
- Within 30 days of receiving the order
- Possession deadline
- The developer must pay interest within 60 days of receiving the order; possession must be handed over as ordered
- Interest
- 10.70 per annum on amounts paid, calculated from August 21, 2024, until actual handover