Subansiri Lower project: To fund hydel project, NHPC proposed its forest land assets as collateral, Govt said no · indianexpress.com

The NHPC wanted to use some of its land and buildings on forest land as a guarantee to get money for a big dam project called Subansiri Lower.

The government said no because the rules don't allow using forest land for such purposes.

The project is very expensive and has faced many delays.

Right now, only one part of the dam is working, and the rest will be ready by 2026-27.

The government is strict about not using forest land for anything other than what was originally allowed.

Key facts

Project
Subansiri Lower Hydroelectric Project
Location
Arunachal Pradesh-Assam border
Cost Escalation
Over 300%
Current Project Cost
Rs 26,000 crore
Borrowing Plan
Up to Rs 10,000 crore
Units Operational
1 out of 8 units
Expected Completion
2026-27
Act Involved
Forest Conservation Act, 1980

Quotes

Environment Ministry

Government body responsible for environmental conservation

“a collateral purpose refers to a secondary purpose beyond the principal object for which the forest land was approved for non-forestry use”
indianexpress.com
“Mortgaging the land or assets created thereon for financial gain constitutes use for a collateral purpose and is therefore beyond the scope of approval granted under the Adhiniyam”
indianexpress.com

Official records

Official documents or statements

“NHPC requested for an NOC for using their assets located on the forest land for collateral purpose for raising funds… from the financial institutions to meet the capital expenditure of Lower Subansiri Hydroelectric Project”
indianexpress.com

NHPC

National Hydroelectric Power Corporation, the company managing the Subansiri Lower hydel project

“the project cost increased from Rs 6,285 crores at the 2002 price level to approximately Rs 26,000 crores at the current price level, primarily due to the extended construction period, escalation charges, and interest during construction (IDC)”