Mumbai Developers Ordered to Hand Over Delayed Flats
A consumer commission in Mumbai ruled against real estate developers ERA Realtors and Omkar Realtors.
The developers were found guilty of delaying the handover of flats in their Malad project.
Homebuyers, who had paid large sums for their flats, filed complaints because the developers didn't give them the flats on time.
The commission ordered the developers to give the buyers their flats, along with the occupancy certificates and promised amenities.
They also have to pay the buyers interest on the money they paid and additional compensation for the problems caused.
This decision came after the commission examined the evidence and arguments from both sides.
Developers were found guilty of delaying flat possessions.
The project is located in Malad (East), Mumbai.
The original possession date was agreed upon as June 2019.
Complainants alleged misrepresentation and unsafe construction.
The Commission ordered the handover of flats, plus compensation.
- Who
- Maharashtra State Consumer Disputes Redressal Commission, ERA Realtors, Omkar Realtors, and complainants.
- What
- Ordered developers to hand over delayed flats and awarded compensation.
- When
- Possession was originally agreed for June 2019.
- Where
- Omkar Alta Monte project in Malad (East), Mumbai.
- Why
- Due to deficiency in service and unfair trade practices regarding delayed possession.
- Developer
- ERA Realtors Pvt. Ltd. and Omkar Realtors & Developers Pvt. Ltd.
- Project
- Omkar Alta Monte, Malad (East)
- Commission
- Maharashtra State Consumer Disputes Redressal Commission
- Agreed Possession Date
- June 2019
- Interest Awarded
- 8% annually on payments
- Compensation
- Rs 1 lakh
- Litigation Costs
- Rs 25,000